To November 4th, the national Power Grid Corp of "two cross" (Huainan - Nanjing - Shanghai, Ximeng - Shandong, Ningdong - Zhejiang UHV project) construction mobilization meeting held in Beijing, three UHV project officially started. This is the first batch of the 12 key transmission corridors approved by the national air pollution control action plan, and is the first to start the construction of the UHV project. It indicates that the UHV power grid has entered a new stage of large-scale construction and accelerated development.
Liu Zhenya, the chairman of the national Power Grid Corp and the party secretary, announced the construction of the project. Shu Yinbiao, the director of the company, the general manager and the member of the Party group, attended the conference and spoke. Cao Jianlin, Vice Minister of science and technology, Wang Yumin, deputy director of the National Energy Bureau, Liu Hua, chief engineer of the Ministry of environmental protection, Zhang Gong, vice mayor of Beijing, Wang Bo, vice chairman of the Inner Mongolia Autonomous Region, Zhou Bo, vice mayor of Shanghai, and vice chairman of the Ningxia autonomous region, Bai Xueshan, attended the conference. Shuai Junqing, the deputy general manager of the company and the member of the Party group, presided over the conference.
The total investment of the UHV project is 68 billion 300 million yuan, the total capacity of the new transformer (converter) is 4300 kV (kilowatt), and the new transmission line is 4740 km. The plan has been completed and put into operation in 2016. The total number of the two UHV projects has been increased by RMB. Among them, Huainan - Nanjing - Shanghai UHV AC project via Anhui, Jiangsu, Shanghai 3 provinces (city), Nanjing, Taizhou, Suzhou 3 new substations, the expansion of Huainan, West Shanghai two substations, substation capacity of 1200 KVA, the new transmission line 2 x 780 km, 26 billion 800 million yuan investment project; Ximeng - Shandong UHV AC project via Inner Mongolia, Hebei, Tianjin, Shandong 4 provinces (autonomous regions and municipalities), the new compensation station Ximeng, Beijing East, Ji'nan and Chengde on 3 substations, substation capacity of 1500 KVA, the new transmission line 2 x 730 km, 17 billion 800 million yuan investment project; Ningdong Zhejiang HVDC the project in Shaanxi, Shanxi, via Ningxia, Henan, Anhui, Zhejiang 6 provinces (area), Ningxia East, Shaoxing 2 converter stations, the converter capacity of 16 million kilowatts, line length of 1720 km, 23 billion 700 million yuan investment project .
Wang Yumin said, "the two way has been" UHV project is a key transmission channel project of air pollution control action plan, which is significant for meeting the demand of electricity consumption in Beijing, Tianjin and Yangtze River Delta, and alleviating environmental pressure. Large scale and long lines, tight and heavy task, the national Power Grid Corp should cooperate closely with the governments at all levels along with engineering, engineering design, construction, supervision and equipment manufacturers of unity and cooperation, strengthen organizational leadership, careful arrangements, strict management, scientific construction, high quality, high level and high standards to complete the construction tasks, to ensure that the 2016 at the end of the completion of all, play a role, to achieve the solemn commitment of the CPC Central Committee and State Council, a energy industry energy saving and emission reduction, the haze of governance, to satisfy the society.
Cao Jianlin said that the national Power Grid Corp with a high sense of responsibility and dedication, striving to promote the UHV transmission technology research and practice, made a series of technical breakthroughs in UHV transmission theory, technology, equipment, standards, access to a number of innovations with independent intellectual property rights, formed a relatively complete system of UHV technology the increase of China's influence and voice in the International Electrotechnical field. The successful implementation of the "two way to go" UHV project will play an important role in optimizing energy structure, harnessing haze and realizing clean, efficient and sustainable development of energy. As in the past to support the national Ministry of science and technology Power Grid Corp independent innovation ability construction, support of UHV transmission technology research and development, but also hope that the national Power Grid Corp of scientific and technical personnel and project builders continue to push China's UHV transmission technology research and engineering construction, to further expand the China lead in UHV transmission technology field, make our country firmly grasp the development opportunities and take the initiative in the new round of world energy and technology revolution.
Liu Hua said that in recent years the national Power Grid Corp actively the development of UHV power grid, the implementation of alternative energy, fully comply with the air pollution prevention action plan to accelerate the adjustment of energy structure, increase the deployment of clean energy supply, in the long run, but also to promote the adjustment of energy structure, promoting clean development the only way which must be passed. "Two cross has been UHV project is completed, will comprehensively promote the southwest, Ximeng, Ningdong base of large energy intensive development, optimization of energy distribution, effectively reduce the coal consumption of the eastern region, promote the reduction of sulfur dioxide, nitrogen oxides, soot pollution. I hope the national Power Grid Corp continue to attach great importance to environmental protection work, adhere to the development, in the development of protection in the protection of the principle, to speed up the UHV power grid especially the construction of key transmission channel in the air pollution control action plan, and make new contributions to improve the atmospheric environment in china.
Shu Yinbiao said that in May of this year, the state decided to speed up the construction of 12 key transmission channels including air pollution prevention and control plan, including the "four to four" UHV project, which is required to be completed by 2017. The national Power Grid Corp attaches great importance to and concentrates its efforts to accelerate the early work of the project in an all-round way. Today's construction of the "two way to go" project is the first approved UHV project in the action plan for air pollution control. It has opened the prelude to speeding up the construction of the "four intersection, four straight" UHV project, which is of great significance. The "two way to go" project involves 13 provinces (autonomous regions and municipalities). It will build 1 million volts, two towers, 1510 km and 800 thousand V DC lines 1720 kilometers, and the substation / converter capacity of 4300 kV (kw). The plan is completed in 2016. It is difficult to build and coordinate the large scale of the project, the long battle line, the tight schedule, the heavy task, and the more cross - span with the railway and the highway. The national Power Grid Corp will cooperate closely with all levels of Party committees and governments along the line of the project, carefully organize and plan carefully with the support and support of the relevant ministries and commissions of the state, so as to speed up the construction of the project. The important significance of all participating units and employees should have a profound understanding of the engineering construction, in accordance with the construction of "safe, efficient, green environmental protection, the international first-class quality engineering requirements, scientific construction, strict management, strengthen the implementation of investment control, protect the environment to the requirements, pay close attention to safety, quality and schedule, high standard and high level to ensure the completion of construction tasks, completed in 2016 put into operation.
The Ningxia Hui Autonomous Region, Shanghai, the Inner Mongolia Autonomous Region City, Beijing municipal government leaders to "two has been UHV Construction warm congratulations, certainly UHV project to meet the important role of local economic development and the demand for electricity, improve the environment, said it would strengthen strategic cooperation with the company, coordinate and solve the difficulties and problems in engineering in the construction of the building to create a good environment and conditions for the project, built in the early, early results.
Bai Xueshan said, Ningdong - Zhejiang UHV project is one of the air pollution prevention action plan 12 key transmission channel, Ningxia is also the second power delivery channels, to ensure the power supply in Zhejiang, improve the ecological environment in East China, driven by Ningxia and other western regions development has great significance, is the Ningxia autonomous Region People's highly anticipated large projects, large projects, will bring new opportunities for the development of Ningxia. The government of the autonomous region will do the project coordination services, to promote the power supply point synchronous construction, actively coordinate and solve the problem of project construction, and the relevant state ministries, national Power Grid Corp joint efforts, the project will create a demonstration project of power transmission from west to east to high engineering, construction model.
Zhou Bo said that the demand for electricity in Shanghai is large, but there is a lack of primary energy. It is urgent to speed up the development of UHV power grids, expand the scale of external power receiving in Shanghai, and meet the needs of Shanghai's future electricity consumption and economic sustainable development. Shanghai city has always attached great importance to and support the construction of UHV power grid, and the national Power Grid Corp jointly established the UHV construction leading group, and specifically the establishment of a joint meeting system of electric power construction, the organization held a special meeting, the construction of refinement responsibility, clear and specific tasks to ensure that the Huainan - Nanjing - Shanghai UHV project completed on schedule and quality. The governments at all levels in Shanghai will continue to fully support the development of the national Power Grid Corp and the development of Shanghai power grid, making joint efforts to make new and greater contributions to the sound and fast development of the economy and society.
Wang Bo said that Inner Mongolia is rich in resources such as coal and wind power. It is an important national energy area and a large power transmission area. "Mongolia transmission" greatly supports Inner Mongolia's economic and social development. It can be said that relying on UHV to integrate into the large power grid to promote the optimal allocation of Inner Mongolia's energy resources across the country is an inevitable choice to promote Inner Mongolia's energy and resources advantages into better economic advantages. The Inner Mongolia Autonomous Region will further strengthen the strategic cooperation with the national Power Grid Corp and all aspects of the project, go all out to do the coordination and service guarantee, with the fastest speed, the highest efficiency, best service to create the best environment construction, and strive to Ximeng - east mountain high, early completion of the project will play a role.
Zhang Gong said, today started construction of the Ximeng - Shandong UHV project, the eastern region of Inner Mongolia Everfount clean power into Beijing. The construction of the project is of great significance for meeting the needs of the capital and improving the environmental air quality. It is a basic engineering, environmental protection project and Huimin project in the contemporary era and in the long run. Beijing municipal government will continue to strengthen strategic cooperation with the national Power Grid Corp, organize and mobilize the various forces to support the project construction, timely coordinate and solve the difficulties and problems in project construction, and strive to create a good environment and conditions for construction project as soon as possible, to play a role.
At present, the company completed a total of two pay four straight UHV, in the construction of UHV transmission line length of more than 15 thousand kilometers, the substation (converter) capacity of more than 1.6 million KVA (kw), a total of more than 250 billion kwh of electricity. The flood season this year, to maintain safe operation of full power complex Feng, Jin Su, binkin three special HVDC project long time, carrying more than 80% Sichuan hydropower delivery task, to the east of the southwest region of mass transport clean water and electricity 60 billion kwh, accounting for about 2/3 of electricity by Eastern china. Relying on the development of new energy sources in large power grid, the new power grid installed capacity of the State Grid has reached 100 million kilowatts, including 77 million 990 thousand kilowatts of wind power and 18 million 350 thousand kilowatts of solar power. The State Grid has become the largest grid with the largest wind speed and the fastest growth rate of solar power generation in the world.
The main venue of this conference is located at the headquarters of the national Power Grid Corp. The sub venues are located at the engineering site of Shandong, Jiangsu and Ningxia, as well as the Beijing electric power network, Beijing, Tianjin, Hebei, Shanxi, Shanghai, Zhejiang, Anhui, Henan, Mongolia East, and the Ministry of electric power.
In the main hall to attend the meeting of leading comrades Wang Yupu vice president China Academy of engineering, the SASAC Development Planning Bureau Chief Deng Zhixiong Wu Xiao, deputy director of the NDRC Department of basic industries, the Ministry of land protection department deputy inspector Liu Renfu, general manager of Huaneng Group, Datang Group Chairman Cao Pei Xi, Chen Jinhang, director, Huadian Group Corporation Manager Cheng Nian Gao, director, China Guodian Corporation General Manager Chen Feihu, general manager of China Power Investment Corp Lu Qizhou, general manager, Chinese power construction group company director Yan Zhiyong, China Energy Construction Group Chairman Wang Jianping.
At the venue to attend the conference leaders: Ningxia Autonomous Region Chairman Liu Hui, vice chairman Li Rui, deputy director of the National People's Congress and CPPCC Vice Chairman Wu Yucai Zhang Leqin, vice mayor of Tianjin Yin Hailin, vice governor of Hebei province Xu Ning, vice governor of Shanxi province Fu Jianhua, vice governor of Shandong province Zhang Chao, Shanghai municipal government deputy secretary general Dai Haibo, Jiangsu executive vice governor Li Yunfeng, Deputy Secretary General of the Zhejiang provincial government of Anhui Province, Xia Haiwei, deputy governor Zhanxia, vice governor of Henan province Zhang Guangzhi, the Inner Mongolia Autonomous Region CPPCC Vice Chairman Liang Tiecheng, executive vice governor of Shaanxi Province in the Yangtze louis.
Source of information: National Grid newspaper